Project · Cobourg, Ontario
315–325 University Avenue West.
A four-storey residential building over underground parking, taken from drawings to building permit with one company responsible for the whole mechanical picture — the heat pump plant, the distribution, and the plumbing under it.
The scope
The clearest example of "total project engineering".
On the 501 Alliance retrofit the story is scale. Here it is breadth. This building was engineered as one system rather than as a heat pump with somebody else's plumbing bolted underneath it — underground services, plumbing, the heat pump plant and the distribution to all four floors were taken off and specified together.
The central plant
A shared water source heat pump loop serves the whole building, with supply and return risers stepping down from 4-inch mains to 3-inch, 2½-inch, 1-inch and ¾-inch branches as they reach each floor and each suite. That taper is the quiet part of a good design: get it wrong and the top floor never gets its flow.
The make-up air unit runs on its own circulation circuit with 40% glycol, because the one part of the system that sees outdoor air is the one part that can freeze.
| Building | 4 floors + parking |
| Plant type | Central WSHP loop |
| Expansion tank | Clemmer, 217 US gal |
| Loop pumps | Bell & Gossett Series 80 |
| MUA circuit | Dedicated, 40% glycol |
| Risers | 4″ mains → ¾″ branches |
| Also engineered | Plumbing + underground |
| Stage reached | Issued for permit |
A 217-gallon expansion tank is not a detail
It is the tell for how much water is in the loop, and therefore how much thermal mass the building has to ride out a demand spike. Undersize the expansion volume on a multi-storey shared loop and you get pressure faults on the coldest morning of the year — which is exactly when nobody wants to be diagnosing a plant.
Why it matters to you
Multi-residential is where split responsibility hurts most.
On a house, a bad handoff between the driller, the mechanical contractor and the equipment supplier costs you a week. On a four-storey shared-loop building it costs you a heating season, because nobody owns the number that turned out wrong.
- One takeoff covering plumbing, mechanical and underground, so nothing falls between two trades' scopes at tender.
- Equipment selected against the design rather than the design bent around whatever equipment was available.
- Drawings that survive a building-permit review, because they were drawn to be built rather than to win a bid.
Resource
Bring the drawings early.
The earlier a shared-loop plant is considered, the cheaper it is — risers and mechanical space are almost free on paper and brutally expensive later.
The capability brochure has the figures for this project and for the 275-ton retrofit, in four printable pages.